Falconbridge plans extended mine shutdown (5/02)

Falconbridge Ltd. is planning an extended summer shutdown of its Sudbury smelter from June 18 to Aug. 8. Company officials say the 52-day maintenance and vacation shutdown is to ensure its facility runs at 100 per cent peak annual efficiency.

Falconbridge Ltd. is planning an extended summer shutdown of its Sudbury smelter from June 18 to Aug. 8. Company officials say the 52-day maintenance and vacation shutdown is to ensure its facility runs at 100 per cent peak annual efficiency. The savings of the cost-cutting move will not be known until the end of the fiscal year. About 250 workers will be affected. Normally maintenance shutdowns run from June 18 to July 7 at the smelter, while vacation shutdowns run from July 8 to Aug. 8. Falconbridge's mining and milling operation in Sudbury will also undergo a maintenance shutdown from July 14 to July 28. Technical improvements at smelter has boosted capacity, but outstripped the available nickel ore fed to the facility.