Cliffs Natural Resources expects the
environmental assessment (EA) for its ferrochrome processing facility
in Capreol to be complete and submitted for government review by the
first half of 2013, with approval coming by mid-2014.
The company, which is planning to
develop its Black Thor chromite deposit in the Ring of Fire area of
the James Bay Lowlands, outlined the current stage of the EA process
during a media briefing and public open house in Capreol on Oct. 25.
The session was designed to provide an update on the EA process and
glean input from residents.
Jason Aagenes, Cliffs’ director of
environmental affairs for ferroalloys, said all four components of
the project—the mine, concentrator, transportation corridor and
ferrochrome processing facility—are being subject to the combined
provincial and federal environmental assessment, which is moving
forward as an integrated process.
“The purpose of the environmental
assessment is to take a look at the existing environment—and we’ve
been conducting baseline monitoring for a couple of years now—then
take a look at the project as it’s designed and you estimate any
impacts on the existing environment,” Aagenes said.
The EA studies impacts to the human
element, including First Nations land use, health and safety and
socioeconomic factors; the physical element (land, air, water); and
the biological element (fish, wildlife, vegetation, insect life).
The project will then be redesigned to
eliminate, mitigate or otherwise reduce any anticipated negative
impacts, Aagenes added. A number of the project’s components are
still being determined, including the mine site layout, a water
source, a method for discharge of treated affluent, and mine closure
and decommissioning.
Though early in the EA process, Aagenes
said Cliffs has been consulting with federal and provincial agencies
for more than two years to develop this amalgamated approach. Cliffs
volunteered to undergo the most rigorous type of provincial EA, an
individual assessment, even though it wasn’t required, he said.
“It’s consistent with our interest
in having a robust environmental assessment—everything is
adequately covered—but it also matches up very well with the
federal comprehensive study,” Aagenes said. “The two of these
processes match together very well, so it lent itself to an
integrated approach.”
Designed for a 30-year life span, the
single open-pit mine will move 110,000 tonnes of material per day.
It’s estimated 3,300 tonnes of concentrated ore will be transported
down a 340 km-long all-weather road and transferred to rail before
reaching the processing facility in Capreol. That translates to about
100 85-tonne trucks per day, or one truck every 15 minutes.
Concentrate will be packed into sealed
boxes similar to cargo containers found on ships or
transport-trailers and remain sealed until they arrive at the
processing facility. “The first time they’re opened will be
inside the furnace building here in Capreol,” Aagenes said.
The containers will be opened,
unloaded, closed and shipped back to the mine site for reuse.
Aagenes said community consultation is
not only important to inform the design of the project, but it’s
also a requirement of the EA process. Community and government
consultation will continue throughout the development process, he
said.
Integral to that is input from the
seven nearby First Nations, including Wahnapitae First Nation,
located just outside of Sudbury, which is assisting Cliffs with its
environmental review process.
“We rely on their expertise and
knowledge of the area to help inform the environmental assessment,”
Aagenes said.
Once the EA is submitted for government
assessment, the review period lasts an average of 62 weeks, but can
start and stop depending on the public consultation periods mixed in
throughout that review period, Aagenes said. The idea is to provide
plenty of opportunity for public review.
Permitting for the project will follow
immediately after the EA is approved. Aagenes said much of the
permitting process is being conducted in parallel to the EA process,
since many of the same agencies are involved.
Cliffs’ is still aiming to have its
entire operation up and running by 2016, but that could change,
depending on the results of the EA and the feasibility study, which
are being conducted simultaneously, Aagenes said. The company will
then assess the findings of the two reports, industry conditions and
Cliffs’ cash position to make its final decision on startup.
“We’ve always acknowledged we’re
in the feasibility stage of this process,” Aagenes said. “There’s
still a lot of work that has to occur, so the schedule will be
evaluated after these pieces come together.”