New Red Lake gold mine edges closer to production

Rubicon Minerals reports its Phoenix Gold project in Red Lake remains on schedule to start production by mid-2015.

Rubicon Minerals reports its Phoenix Gold project in Red Lake remains on schedule to start production by mid-2015.

The mill commissioning process is ahead of schedule and is expected to continue throughout this year’s second quarter, including limited processing of some low-grade development material.

Company president-CEO Michael Lalonde said they’re in the “homestretch” toward the projected initial production. “The stockpiling of mill feed continues. We expect that all remaining underground development prior to projected initial production will be completed by the end of May.”

As of April 12, 85 per cent of the underground development work was complete.

Eight stopes are in various stages of development between the 122- and 305-metre levels. The company, which has stockpiled 11,600 tonnes of mineralized material, said it will keep stockpiling as stope development accelerates and mining begins.

The processing of mineralized material on an ongoing basis will take place sometime during the middle of this year. The tailings facility is ready to accept two years of tailings from the operation. and the remaining surface and on-site construction work is nearing completion.